PLTM Kalibumi I

Ringkasan Proyek
The project is funded by KfW under the Hydropower Programme with a loan totaling EUR 69.7 million (≈USD 76.7 million). The total project cost, including both EPC and non-EPC expenses, amounts to USD 42.4 million. Currently, PLN is in the process of finalizing the Detailed Engineering Design. However, based on the updated feasibility study, there is a shortfall in the loan amount required to fully cover the EPC costs.
Kode Proyek
PH-01-26-1124
Kategori Proyek
Financing Project
Teknologi
Hidro
Jenis Proyek
OnGrid (terhubung)
Transmisi/Pembangkit
Pembangkit
Lokasi Proyek
Nabire Regency
Khusus (provinsi)
Papua Tengah
Pengembangan
Tahun CoD yang Diharapkan
2027